About Project Risk Management
What is
Project Risk Management?
Project risk
management is project management for grown ups.
Most projects lose
money through the occurrence of unexpected events. Although unexpected,
such events are usually predictable; often the same problems are
encountered on project after project.
While some project
professionals work to prevent the unexpected, many people working on
projects accept such financial losses as something that is normal.
Project risk
management does not accept these losses. Project risk management actively
identifies risks before they occur, prioritises these risks, and reduces
the risks in the most cost effective ways available.
Back
to top.
Why use Project Risk Management?
Without guidance, many engineers will work on the tasks they are most
familiar with, work that is expected.
Without guidance, many planners will concentrate on ‘the critical path’,
not realising that many other paths can be come critical as a result of
unexpected events.
Without guidance many QS’s will concentrate on reducing the value of
budgeted costs, or maximising the value of compensation events once an
unexpected event has occurred. The gains from this approach are often
small, and result in confrontational relationships with sub-contractors
and clients. These approaches have their own potential long-term financial
problems.
Effective project risk management gives meaningful financial costs to
unexpected events. These costs are then aggregated and added to the
expected out-turn cost of the project.
By
doing this, the attention of all parties working on the project are
focussed on where money is actually likely to be lost. If this is done in
a timely manner, mitigation can be put in place at minimal cost, and the
out-turn cost of the project can drop sharply.
Accurate financial risk assessment of projects when tendering can give a
much greater confidence in a price offered to a client. As projects become
more complex, a contractor that can show effective risk analysis at tender
stage is much better placed to convince a client of their competence.
Back to top.
Why projects go over budget
Projects go over budget for a number of reasons:
‘Best-case’ prices are put in the budget, but no allowance is put in for
not being able to always achieve the best-case price. Statistically,
it is likely that some price will not be best-case, so the out-turn cost
rises above the budget.
‘Most-likely’ prices are put in the budget, but it is not appreciated that
the distribution of likely prices is heavily skewed towards increasing
rather than decreasing. Statistically this means that the likely
total cost is higher than the sum of all the ‘most-likely’ prices, so the
out-turn cost rises above the budget.
Unexpected events are ignored, fingers are crossed, and it is hoped that
risks will not materialise. Statistically, many unexpected events can
happen on a project, so a few of them will, so extra costs arise that were
not in the budget.
Risks are recognised, but it is assumed that risks with low probability
will not occur.
Statistically, if you have a significant number of risks with low
probability, then some of these risks will occur, so extra costs arise
that were not in the budget.
Risks occur that affect the programme, so causing extra spend and
liquidated damages.
Back to top.
Why
projects go late
Projects go late for two main reasons:
As
with cost risks, time risk distributions are strongly skewed. It is much
more likely that the actual time taken for an activity is longer than the
‘most-likely’ time put in the programme, rather than shorter. Activities
are more likely to be late than early. Statistically, these extra times
build up over the programme.
More
importantly, schedule risk works differently to cost risk. Cost risks tend
to average out, some go up, but some come down, there is some averaging at
work.
Time
risks are different. When any activity has more than one predecessor, that
activity can not start until all proceeding activities have finished. The
start of the activity is always defined by the latest of its predecessors.
Time
risks are always worst case, and so they add up much more aggressively
than cost risks. These problems are worst where the programme has a lot of
merging branches, usually in the final third of the programme.
When
the skewed nature of time risk distributions is combined with the problems
of merging branches, it is found that most projects have many potential
critical paths.
Back to top.
How to bring
projects in on time & to budget
At
the beginning of the project:
-
Identify all possible risks that could affect the project
-
Quantify the risks in pounds and pence
-
Add
up the total risks in a statistically meaningful way
-
Quantify the programme activity durations with meaningful risk spreads
-
Analyse the programme to give a statistically meaningful end date
-
Calculate the extra costs and liquidated damages if the programme shows a
likely over-run.
-
Add
these costs to the cost risk totals
-
Add
this total risk budget to the predicted out-turn cost of the project
Each
month during the project:
-
After the spend to date, review the risk budget as part of the expected
spend to completion
-
Identify any new risks
-
Check the values of the existing risks
-
Prioritise the risks according to their financial impact
-
Put
in place mitigation to reduce the risks with the large impacts
-
Review the critical items on the programme
-
Put
in place mitigation for the items with the biggest time impacts
Most
contractors have a monthly managerial process in which the project manager
states the spend to date on the project, and the spend to completion. Due
to unforeseen events, the spend to completion will often be above the
budget cost of the project. The project manager’s superiors will then
often take considerable efforts to dissect and criticise the extra
expenditure that has been incurred.
The
aim of the process as described above is to move this analysis and
criticism to a time before the extra expenditure has occurred. If this is
done effectively then the extra expenditure can be avoided.